Fenner Conveyors

Completion Date 18/07/2025 (10 Weeks ahead of construction program)
Category: Industrial Construction Perth
Client: Fenner Conveyors Pty Ltd
Location: Kwinana WA
Contract Value: $21.6M ex GST (including Design Contract)
Architect: Shelford Construction

Facility Overview

Shelford Constructions successfully delivered a large-scale industrial construction Perth project for Fenner Conveyors Pty Ltd in Kwinana, WA, designed to support the production of rubber blocks used in conveyor belt manufacturing.

This $21.6 million purpose-built facility includes four interconnected buildings:

  • Main Production Building (4 storeys, 31m height)

  • Storage Building

  • Admin Building

  • Control Building

The project was designed with operational efficiency and future growth in mind, including provision for a second production line.

Key infrastructure and inclusions:

  • 5-tonne goods lift and 2-tonne passenger lift

  • 35-tonne gantry crane and loading dock

  • 1,000m² drainage swale and 2,000m² landscaping

  • 900m² mural artwork across main and storage building façades

  • Admin building carpark and all associated services including fire, security, hydraulic and electrical

Key Features

  • 31m-high industrial production facility

  • Integrated design and construction delivery

  • Heavy-duty lifting and crane infrastructure

  • Provisions for future production line expansion

  • Landscape and drainage works to industrial spec

  • Architecturally integrated mural work (900m²)

Project Challenges

Delivering a 31m-high industrial building involved intensive planning and high-risk coordination, with 90% of construction tasks classified as high-risk. Additional complexities included:

  • Concurrent machinery installation by the client during Shelford’s internal fit-out works—requiring detailed HSE planning to ensure zero incidents

  • Western Power’s late-stage requirement for a new HV Building, which was managed and completed within the original timeframe

Despite these challenges, Shelford Commercial delivered the project 10 weeks ahead of schedule, a testament to our planning, safety, and delivery capabilities in the industrial construction sector in WA